A.
The applicant or developer of the land development activity or his representative shall at all times properly operate and maintain all facilities and systems of treatment and control (and related appurtenances) which are installed or used by the applicant or developer to achieve compliance with the conditions of this chapter. Sediment shall be removed from sediment traps or sediment ponds whenever their design capacity has been reduced by 50%.
B.
The applicant or developer or representative, one of which must be a trained contractor, shall be on site at all times when construction or grading activity takes place and shall inspect and document the effectiveness of all erosion and sediment control practices. Inspection reports shall be completed every seven days and within 24 hours of any storm event producing 0.5 inches of precipitation or more. Inspection reports shall be delivered to the Stormwater Control Officer and copied to a site log book.
[Amended 2-22-2011 by L.L. No. 2-2011]
C.
For land development activities as defined in § 281-8 and meeting condition 1, 2, 3 or 4 in § 281-10B, the applicant shall have a qualified inspector conduct site inspections and document the effectiveness of all erosion and sediment control practices every seven days. Inspection reports shall be maintained in a site log book.
[Added 2-22-2011 by L.L. No. 2-2011]
D.
Construction activities disturbing five acres or more at any one time shall be inspected by a qualified inspector twice every seven days.
[Added 2-22-2011 by L.L. No. 2-2011]