[Ord. No. 123, §2; Ord. No. 197, §2]
In the making of excavations in any street, highway or public place, the excavated materials from the trenches shall be placed where they will cause the least possible inconvenience to the public. The width of excavation shall be no greater than is necessary for doing the work and sheathing and bracing shall be used as necessary, to keep the sides of the trench vertical and to prevent caving. Adequate provision for proper drainage of the areas surrounding the work shall be maintained at all times.
Excavations made in or under street, walk or driveway pavements are to be backfilled with granular material thoroughly tamped into place as hereinafter specified and the pavement surface restored to its original condition. In such locations excavated materials are to be removed from the site of the work as the excavation is made and no such material allowed to accumulate on the site.
Substitution may be made for granular backfill only with specific approval of the city street commissioner or plumbing inspector in each instance.
Approved granular backfill material shall be composed of a mixture of crushed stone or gravel and sand, free from clay lumps and trash and conforming to the following sieve analysis:
| Passing 1" screen | 100% |
| Passing ¼" screen | 35 to 65% |
| Passing #50 screen | Not more than 20% |
| Total clay and silt | Not more than 10% |
Other materials may be used only when they have approval. |
|
Granular backfill is to be placed in horizontal layers not greater than six inches thick before compaction and shall be thoroughly compacted by mechanically operated tamping. During placement and compaction care must be taken to avoid undue segregation of coarse and fine particles. |
|
Excavations in parkways, outside of the paved area of streets or walks may be backfilled with earth and all grassed areas returned to their original condition. Earth backfill is to be placed and compacted in the same manner as described for granular fills or thoroughly jetted to obtain maximum settlement and shall be maintained by the person making the excavation until the area has been stabilized in the original condition. As soon as the excavation has been backfilled, all excess excavated materials shall be removed from the area and disposed of. |
|
The actual work of placing and compacting granular backfill and repaving excavated area in paved streets and walks is to be performed by the person making the excavation. |